Digging starts for stalled Seattle tunnel machine

SEATTLE (AP) — Contractors building a new highway tunnel under downtown Seattle have started digging a 120-foot pit to rescue a stalled boring machine named Bertha.

Seattle Tunnel Partners also is pumping out groundwater as it digs the 80-foot-wide pit near the Seattle waterfront.

The $80 million, five-story-tall boring machine overheated and came to a stop last December after digging about 1,000 feet, or about 10 percent of the planned Highway 99 tunnel route. An investigation found seals in the cutting head were damaged.

A crane will lift the cutting head from the pit for repair. Tunneling could resume in March.

___

Information from: Seattle Daily Journal of Commerce, http://www.djc.com/

Copyright 2014 The Associated Press. All rights reserved. This material may not be published, broadcast, rewritten or redistributed.

Quiz: Things you might not know about July 4

WASHINGTON — How well do you know your Independence Day trivia? Take our quiz. [custom_gallery]
Read Next Story