SPRINGFIELD, Ill. (AP) — The Chicago Transit Authority on Friday filed a federal lawsuit seeking restoration of $2 billion in commuter rail expansion funding that President Donald Trump’s administration stopped last fall.

The action, filed in U.S. District Court in Chicago, contends the administration acted arbitrarily in halting transit construction money for the city in an effort to restrict race- and gender-based contracting, which it believes is unconstitutional. It names the U.S. Department of Transportation and the Federal Transportation Authority as defendants.

The Transportation Department responded that it is trying to choke off a “discriminatory” and “illegal” contracting process.

The lawsuit comes days after New York City authorities filed a lawsuit seeking resumption of similar federal transit funding to the tune of $60 million.

Critically affected in Chicago is a 5.3-mile (8.5 kilometer) extension of the Red Line of the elevated L rail system with four train stops to reach 100,000 additional residents in disadvantaged and largely Black neighborhoods. Additionally, the federal dollars had been financing continued work on a North Side project that replaced century-old rails and built four new, accessible stations.

“We are fully committed to the success of these projects, and we will take every step necessary to ensure that they move forward,” CTA Acting President Nora Leerhsen said in a statement. “The Red Line extension is a historic investment into the far South Side of Chicago that will transform public transit and create new economic opportunity for the communities it will serve.”

In September, the Trump administration wrote a new rule removing race- and gender-based contracting preferences but applied the rule retroactively only to grants to Chicago and New York, according to the lawsuit. The grant funding was paused on Oct. 3, 2025, and the CTA provided requested documentation a few weeks later.

The Transportation Department requested additional records in December, and since the CTA responded, there has been no further communication, according to the lawsuit, which calls the government’s actions “unlawful many times over.”

It complains that the holdup penalizes the CTA for following the rules in place at the time and for failing to “explain why grants to the hundreds of other projects nationwide” that were following the same rules saw no interruption in funding.

The Transportation Department said in an email that it will fight “discriminatory, illegal, and wasteful contracting practices.”

“The American people don’t care what race or gender construction workers, pipefitters, or electricians are,” the department said. “They just want these important projects built quickly and efficiently.”

Between prices and a diarrhea-causing parasite, lettuce is causing hard times at some restaurants

It’s been a choppy year for restaurants that lean into lettuce. Lettuce prices rose sharply in the first half of 2026 due to hot weather in Arizona, where about one-third of America’s lettuce is grown. Now, restaurants are dealing with the fallout from a cyclospora outbreak linked to shredded lettuce that has sickened thousands of Americans. Taco Bell will likely see the biggest sales impact from the outbreak, which began in late June. Federal health officials first tied the outbreak to shredded iceberg lettuce served at Taco Bell restaurants in Indiana, Kentucky, Michigan, Ohio and West Virginia. Later, the U.S. Food and Drug Administration said customers in Illinois, Kansas, Oklahoma and Pennsylvania were also affected. Taco Bell said on July 17 that it had voluntarily removed shredded iceberg lettuce supplied by Taylor Farms from its U.S. restaurants. But its customer volume has suffered. As of July 23, Taco Bell visits were 21% lower than average across the U.S., according to Placer.ai, a market research company.
Read Next Story